Grid operators and states put conditions on new data-center load in Q3 2026

Utilities, grid operators and their regulators spent the quarter separating data-center demand that will arrive from requests that may not, and deciding who pays for the supply it needs. Inside energy companies, AI stayed mostly at the pilot stage and in vendor-reported task results, and New York ordered its utilities to inventory every use.

Editorial snapshot: 31 October 2026

The central finding

PJM, Texas and New York moved to make new data-center load bring capacity or accept curtailment, pass an audit, or wait for permit standards, while the load forecasts behind those decisions shifted by gigawatts within weeks.

01Key findings

What changed in energy and AI in the third quarter

Most of the quarter's decisions about AI in energy treated AI as a customer. Grid operators, governors and regulators set terms for data-center load, and equipment makers sold turbine capacity years ahead. The industry's own AI use advanced through document review and drilling automation, and New York ordered utilities to inventory it.

Capability

Data centers are being specified as grid devices

FERC directed NERC to write reliability standards for computational loads by year-end, and PJM's board decided that new large loads bringing no capacity by June 1, 2027, will be curtailed ahead of pre-emergency load management. Operational AI advanced mainly in rule-bound document and drilling work, with a person signing off.

Capital

Turbines and firm power absorbed the capital

GE Vernova's gas backlog and slot reservations reached 116 GW, with slots mostly sold through 2030 and first-half equipment orders priced more than 20% above the fourth quarter of 2025. Firm-power developers drew about $6.3 billion in 17 rounds; AI software for energy operations was absent from the largest rounds.

Adoption and economics

Requested load far exceeds load ready to connect

ERCOT held more than 474 GW of large-load interconnection requests; about 205 GW was preliminarily eligible for its first batch study, and 17 loads totaling about 6.6 GW had cleared every step except final energization. PJM's 2028/29 capacity bill reached $16.4 billion, 38% of it attributed to data centers by the market monitor.

Accountability

PJM fell short and turned to a backstop

PJM's 2028/29 capacity auction cleared at its price cap and 6,831 MW short of its reliability requirement. FERC accepted a one-time backstop procurement subject to refund and a hearing on who pays, while the market monitor argued that about 4,017 MW of forecast data-center load had already been canceled or delayed.

Operating question

For each large-load figure you plan against, can you say whether it is a request, a signed service agreement or energized load, and who pays if it does not arrive?

02Capability

Data centers as grid devices, and where operational AI advanced

The structural technical change in energy this quarter concerned how AI facilities must behave on the grid: how they are modeled, registered and curtailed. Inside operations, AI advanced where work is document-heavy and rule-bound and a person signs the decision. Frontier model releases added two capabilities that bear directly on utilities' control and legacy systems.

Reliability · Standards due by year-end 2026

NERC standards for computational loads

According to Texas Reliability Entity, a FERC order in July directs NERC to develop reliability standards for computational loads by year-end 2026 and to report on further needs by March 2027. NERC posted a data-center load modeling reference on Aug. 3 and put revised standards and registration criteria out for comment and ballot from Aug. 19 to Sept. 18.

Flexibility · Applies from June 1, 2027

Curtailment ahead of emergency load management

Under the Interim Resource Adequacy Service that PJM's board approved on July 27, new large loads that bring no capacity by June 1, 2027, are curtailed before pre-emergency load management. The European Commission's proposed data-center rating scores flexibility alongside energy and water use. In March, Google said it had 1 GW of demand response under long-term contracts with five utilities.

Model data

Dynamic models now decide queue position

ERCOT left 47 large-load projects out of its Batch Zero study because they had not submitted a dynamic model by July 10. PJM will keep a Large Load Registry populated by electric distributors, and the Texas governor's directive requires per-project disclosure of annual and peak power, on-site generation, water use and cooling.

Operations

AI in document review and drilling, with human sign-off

When PJM accepted 715 projects into its first reformed interconnection cycle on Aug. 3, it said it was using HyperQ, from Alphabet's Tapestry, to review application data. Tapestry says the software drafted site-control readiness reports citing the page, clause or coordinate behind each finding, while PJM engineers made the compliance decisions. SLB reported a 2,000-meter well section drilled autonomously for Azule Energy in Angola.

Frontier models

Gated cyber capability and computer use

OpenAI's GPT-6 Astra, launched Sept. 3, is the first OpenAI model rated Critical for cyber capability and can operate applications that have no API, with approval prompts. Google limited Gemini 4 Argon and Gemini 3.8 Flash Cyber to trusted cyber defenders through its Fairwind Program. Utilities running NERC-regulated control systems need that defensive access and are also targets.

Cost and consequence

The quarter's technical requirements are mostly data requirements at the boundary between operator, utility and customer: dynamic load models, registries, disclosure packages and telemetry for curtailment. Frontier models sit within each other's benchmark error bars and differ about fourfold in output tokens per task, so AI tool costs have to be compared per completed task.

03Capital

Capital went to turbines, firm power and existing gas plants

Hyperscalers set the demand. In the third quarter, Alphabet spent $51.4 billion on capital expenditures, Microsoft added $39.4 billion of property and equipment in cash, excluding finance leases, and Meta spent $34.91 billion. Energy capital followed the scarce physical inputs that spending needs, and the largest venture rounds went to firm-power developers whose case rests on data-center offtake.

Disclosed financing

Largest US energy and climate rounds tracked in Q3

Disclosed amounts in USD millions for the nine largest of 22 private energy and climate rounds with US or unconfirmed headquarters tracked in the quarter, which totaled $7.49 billion.

Joulent

Strategic investment — $1.75B

From National Grid Ventures; Joulent is Chevron's power partner on Project Kilby

Commonwealth Fusion Systems

Growth round — $1B

Base Power

Series D — $1B

Valar Atomics

Series B — $1B

Equity; excludes a $200 million credit line

Form Energy

Series G — $750M

Antora

Series C — $550M

Antares

Series C — $370M

Equity portion; excludes $100 million of debt

Sila

Growth round — $300M

Mazama

Series B — $135M

Value Add VC tracker as of Oct. 20; excludes rumored, public and known non-US rounds. Stages as reported by the tracker.

$6.3B

Global venture funding for firm power in Q3, across 17 rounds

Fusion, fission, geothermal and storage, per Net Zero Insights

686

Climate-tech deals worldwide in Q3, the fewest since 2021

Total funding $19.6 billion, down 7.6% from Q2, while equity rose 17%

Utility capex

AEP's plan rests on load at mixed contract stages

AEP set a $78 billion capital plan for 2026 to 2030, implying nearly 11% annual rate-base growth, with about 13 GW of gas turbines secured through 2031 and options on up to 10 GW more through 2035. The load behind the plan includes letters of agreement as well as electric service agreements.

Transactions

Deals for existing gas plants and a utility merger

LS Power agreed Aug. 6 to buy the 606-MW Brazos Valley gas plant near Houston from Constellation, meeting a divestiture commitment from Constellation's Calpine acquisition. The NextEra-Dominion merger, announced in May, moved through approvals, with Virginia evidentiary hearings scheduled from Nov. 17.

Global venture

AI took most of the quarter's global venture funding

Crunchbase counted $159 billion of global venture funding in the third quarter, 64% of it to AI, with 27 rounds of $1 billion or more. Data centers and energy each raised $10 billion or more.

What it signals

For anyone adding generation, the scarce inputs are now priced up: turbine slots are mostly sold through 2030, at first-half prices more than 20% above late 2025, so new capacity costs more and takes longer to arrive. Venture capital for AI applied to grid or field operations did not appear among the large rounds.

04Products

Equipment makers sold out, and oil and gas companies became power suppliers

Gas-turbine makers reported record orders and pricing power, and the trade press described manufacturing capacity, more than demand, as the constraint across GE Vernova, Siemens Energy and Baker Hughes. Oil and gas companies moved into supplying power and building data centers, while their digital and AI lines grew more slowly.

Power equipment and services results reported in the quarter

Company-reported figures. GE Vernova, Siemens Energy and Baker Hughes reported quarters ending June 30 during July and August; SLB reported its third quarter on Oct. 23.

Power equipment and services results reported in the quarter
Company and period Orders and backlogData-center businessPricing and outlook
GE Vernova, Q2 Orders and backlog $24.2B orders, +88% organic; $176B backlog Data-center business About 20% of 116 GW gas backlog and reservations Pricing and outlook Slots mostly sold through 2030 First-half orders priced more than 20% above Q4 2025
Siemens Energy, fiscal Q3 Orders and backlog €17.9B orders, a record; €162B backlog Data-center business Gas Services orders €9.97B, +61.9% Pricing and outlook Fiscal 2026 guidance confirmed
Baker Hughes, Q2 Orders and backlog $10.5B orders, +49%; IET orders $7.09B, +101% Data-center business 76 NovaLT16 turbines, about 1.3 GW, for Dynamis Pricing and outlook Record $37.1B in IET remaining performance obligations
SLB, Q3 Orders and backlog Revenue $9.45B; Digital $693M, +5% Data-center business Data Center Solutions $230M, +76% year on year Pricing and outlook Digital annual recurring revenue $1.04B, +13%

Siemens Energy does not disclose a data-center share of its orders; trade press linked its gas orders to US demand that includes large data-center projects.

Oil and gas

Chevron as a behind-the-meter power developer

Chevron's Project Kilby, agreed before the quarter, dedicates 2.67 GW of gas-fired supply to Microsoft data centers in Reeves County, Texas, for 20 years from 2028. Chevron's New Energies president told Fortune that concern about consumer power prices moved hyperscalers toward reliable, affordable supply including gas, and that Texas officials wanted data centers to bring their own power. ERCOT's gas generation queue grew from 65 GW in June to 80 GW by September.

Electrification

Electrical equipment scope per gigawatt of data center

GE Vernova booked $2.7 billion of data-center electrification orders in the second quarter and more than $5 billion in the first half, more than double its 2025 total. It puts its electrification scope at about $300 million per gigawatt, potentially two to three times that with medium-voltage UPS and solid-state transformers, and called the shift of AI facilities to 800-volt DC an open question.

Oilfield services

Oilfield-services capacity redeployed to data centers

SLB is building a Canadian facility as Meta's modular data-center assembly partner, opening in the first half of 2027. Baker Hughes booked turbine orders from Kodiak Gas Services for 1 GW initially, with a path to 1.8 GW, for data centers and energy infrastructure.

Digital

Oil and gas AI runs on premises

SLB's Lumi data and AI platform and its Brunei Shell contract for Petrel and Techlog with AI features run on premises. TotalEnergies signed a 15-year DrillPlan contract, and Chevron joined the SLB-TotalEnergies digital subsurface collaboration. Baker Hughes reported Cordant awards with SINOPEC, Petrobras and KNPC without performance metrics.

Utilities

Named utility AI uses in New York

Reporting on New York's AI proceeding, Utility Dive named Con Edison using AI for customer service and system inspections, National Grid using GridCARE to analyze interconnection capacity and NYPA analyzing drone data for vegetation management.

Offtake

Hyperscalers anchored clean-power contracts

Utilities, hyperscalers and corporate buyers signed about 31.2 GW of clean-power contracts from January through August, according to S&P Global Commodity Insights. They included about 1.9 GW for Google with Xcel Energy in Minnesota and about 1.5 GW with Cypress Creek in Arkansas.

05Adoption

Data-center load by stage, utility AI use and who pays

Energy has two adoption stories. Utilities' own AI use is measured mainly as pilots, in one survey of investor-owned utilities. AI's demand on the grid is measured at many stages, and each stage means something different: a request, a study slot, a letter of agreement, a service agreement, a forecast or an energized meter. In the third quarter, costs flowed through PJM's capacity market and state large-load rules.

Data-center load from request to meter

Figures come from different operators, utilities and buyers, at different contract stages, and are not additive.

Data-center load from request to meter
Stage FigureReported byDate or basis
Interconnection requests Figure More than 474 GW from more than 1,800 projects Reported by ERCOT, as cited by the governor and The Texas Tribune Date or basis Aug. 3; about 90% of new requests are data centers
Eligible for a planning study Figure About 205 GW Reported by ERCOT Batch Zero, preliminary Date or basis Data as of July 28
Backed by service agreements or letters of agreement Figure 69 GW through 2030 Reported by AEP, including 45 GW in ERCOT Date or basis July 30 earnings call
In various stages of contracting Figure More than 53 GW; about 12 GW under service agreements Reported by Dominion Date or basis July 31 earnings call
Grid-operator forecast Figure About 70 GW of new large load by 2038 Reported by PJM board Date or basis July 27
Forecast load since canceled or delayed Figure About 4,017 MW Reported by PJM market monitor Date or basis 2028/29 auction forecast
Cleared every step except energization Figure 17 loads, about 6.6 GW Reported by ERCOT Date or basis Ramping over about five years
Energized consumption, one buyer Figure 42 TWh in 2025, +38.4% Reported by Google Date or basis Calendar 2025

In ERCOT, requests exceed the load cleared for everything but energization by about 70 to 1.

Investor-owned utilities · Survey fielded April 2026

Utility AI use is measured as pilots

Deloitte's survey of 60 investor-owned utilities measured piloting or deploying, not production use. Only 10% reported high AI and geospatial maturity, and 3% fully integrated resilience planning with enterprise value measurement. New York's regulator said the extent of AI in its utilities' operations was unclear.

100%Piloting or deploying traditional AI

68%Piloting or deploying generative AI

42%Piloting or deploying physical AI

38%Piloting or deploying agentic AI

Forecasts

Load forecasts differ by method

Grid Strategies found in November 2025 that utility forecasts filed with FERC ran about 40% above credible industry projections through 2030. Goldman Sachs projects 66 GW of US data-center demand in 2027, more than double 2025, with only about half of capacity due in the next one to two years arriving on time. Utility Dive summarized both in September.

Vertically integrated utilities

Rate-base growth tied to contract stage

AEP's plan for nearly 11% annual rate-base growth depends on load that mixes service agreements and letters of agreement. It has five large-load tariffs approved and three pending, and says take-or-pay contracts could offset up to $16 billion of fixed costs for residential customers in its vertically integrated utilities over the contracts' lives.

PJM customers

PJM's capacity bill and who carries it

Without the price collar, the 2028/29 bill would have been about $29.7 billion. The monitor attributes $29.4 billion, or 46%, of four auctions' costs to data centers. Unison Energy estimates a 10-MW industrial customer's monthly capacity charge rising from about $6,000 in 2024 to about $70,000 in 2028.

$16.4B2028/29 capacity bill at the price cap

38%Share attributed to data centers by the market monitor

Public power and cooperatives

A qualified opt-out, and over-procurement risk

PJM's backstop filing lets qualifying cooperatives and municipal utilities opt out of its costs, which FirstEnergy called discriminatory. The cooperative NOVEC told FERC its share of the shortfall is 1,303 MW but that it would need to procure about 1,619 MW.

Generators

Scarcity raised generator revenue

Constellation, Vistra and Talen reported higher cleared capacity revenue. The backstop offers new resources contracts of up to 15 years at pay-as-bid prices under a $555/MW-day average cap. In vertically integrated states, by contrast, utilities capture load growth through rate base.

Economics

The largest measurable AI spending in energy this quarter was data-center buyers paying for power, equipment and capacity, and the pressure on utility business models came from AI as a customer. Savings from AI inside utilities do not yet appear at visible scale in rates or earnings. EIA expects the average US residential electricity price to rise 5.2% in 2026, to 18.20 cents per kilowatt-hour.

06Outcomes

Reported results in document review, drilling and queue gating

The quarter's reported results come from the companies that sell or run the systems. They measure speed, deployment or money collected, and none is an independent evaluation. The PJM case is the most useful pattern for grid operators because the software drafts the evidence and an engineer makes the decision.

Grid operator · Vendor-reported

Site-control review for PJM's first reformed cycle

Tapestry says HyperQ reviewed site-control evidence for about 220 GW of projects in under a day, against its estimate of about two months by hand. PJM engineers made each compliance decision. On Aug. 3 PJM accepted 715 projects, about 201.5 GW, into the cycle and said it would evaluate the tool throughout. Tapestry's account is undated and gives no error rates; the review fell between the April 27 close of applications and that announcement.

811Readiness reports

6 min 15 sMedian time per report

Oil and gas · Vendor-reported

Autonomous drilling and fleet operations

SLB reported that its DrillPlan and DrillOps software drilled a well section autonomously for Azule Energy in Angola, and that ADNOC runs an AI-enabled real-time operations center across its rigs. SLB published no time or cost comparison for either.

2,000 mSection drilled autonomously

120+ADNOC rigs in the operations center

Queue gating

Collateral as a filter on speculative load

AEP said it collected nearly $2 billion of cash or collateral against 45 GW of requests in ERCOT's Batch Zero, which it described as a way to separate committed from speculative projects.

Nearly $2BCash or collateral collected

45 GWRequests it covers

Buyer

Google's power use outpaced its clean-energy share

Google's data centers used 42 TWh in 2025, up 38.4%, while the carbon-free share of its electricity slipped from 66% to 65%, according to S&P Global's reading of Google's 2026 environmental report. Google has about 35 GW of clean power under contract.

42 TWhData-center electricity, 2025

65%Carbon-free share, down from 66%

What the results establish

These results show speed on a defined task, deployment at fleet scale and money posted as a gate. None measures accuracy, study quality or cost per completed task, which a commission or board would need before relying on AI in planning decisions.

07Corrections

Four claims about the quarter that need their stage or status

Several widely repeated claims from the quarter drop a distinction that changes what they mean.

Load · Overstated

474 GW is requested load; about 6.6 GW had cleared every step except energization

Claim under review: Texas has 474 GW of data-center demand.

The governor's Aug. 3 directive cited more than 474 GW of requests to connect, with about 90% of new requests from data centers; ERCOT put the queue at more than 1,800 projects. It counted about 205 GW as preliminarily eligible for Batch Zero and identified 17 loads totaling about 6.6 GW that had passed every gate except final energization approval.

FERC · Incomplete

FERC accepted and suspended it, subject to refund and a hearing on who pays

Claim under review: FERC approved PJM's backstop procurement.

The Sept. 29 order accepts the procurement effective Feb. 28, 2027, subject to refund, finds its eligibility rules, caps and pay-as-bid design just and reasonable, and sets a paper hearing on cost allocation, transmission-owner exit and collateral. Chairman Laura Swett called the mechanism deeply flawed and said parts of it require reform.

Federal rule · Out of date

FERC opened six regional show-cause proceedings, and PJM's is in abeyance

Claim under review: FERC issued a national large-load interconnection rule by June.

The energy secretary directed FERC in October 2025 to consider rules for interconnecting large loads, generally above 20 MW. On June 18, FERC instead ordered all six jurisdictional RTOs and ISOs to show cause and proposed no uniform national framework. It put PJM's proceeding in abeyance on Aug. 14, PJM's responses are due Nov. 16, and Chairman Swett said the generic docket would stay open.

Contracts · Needs its stage

Each utility counts a different contract stage

Claim under review: Utilities have tens of gigawatts of data-center load contracted.

AEP's 69 GW through 2030 includes letters of agreement as well as electric service agreements. Dominion described more than 53 GW in various stages of contracting, of which about 12 GW is under electric service agreements, according to a summary of its call. Letters of agreement are not service agreements.

08Accountability

Where forecasts, market design and disclosure failed

The quarter's failures in energy were mostly failures of forecasting, disclosure and market design around AI load, and their costs fell on customers and on projects that were ready. The AI-system risk visible in the quarter was exposure that regulators could not yet see.

Market design

A capacity market that did not add capacity

PJM's two most recent auctions cleared at the cap and below the reliability requirement, and only 525 MW of new or uprated capacity cleared, against 774 MW in the prior auction. Prices capped below new-entry cost and slow interconnection and permitting left administrative procurement as the response. Aurora Energy Research's Julia Hoos warned of a cycle of repeated market interventions.

Forecasting

Procurement sized from a moving forecast

The market monitor told FERC that about 4,017 MW of data-center load in the auction forecast had been canceled or delayed; FERC kept PJM's target. Consumer advocates and Policy Integrity argued that the cost allocation fails if forecasts are wrong, and Illinois' commission asked for a reconciliation mechanism.

6,831 MWBackstop target accepted by FERC

About 3,055 MWShortfall after cancellations, per the monitor

Disclosure

Non-response held the whole Texas queue

Only 28 of 377 companies answered a PUCT survey on water and power use, part of the stated trigger for the governor's audit. Another 47 projects lacked dynamic models. The hold applied to everyone in the queue, including 17 near-ready loads, and ERCOT says Batch Zero will miss its April 9, 2027, completion date.

Reliability

Data centers dropping to backup power

Dominion said a transmission-line fault caused some data centers to switch to backup power and called such events rare, according to a summary of its July call. NERC's Level 3 alert, approved by NERC's board in April, calls for corrective actions so that cleared faults do not trip firm load.

Governance

AI use the regulator cannot see

New York's Public Service Commission said the extent of AI in utility operations was unclear and ordered every electric, gas and water utility to inventory its uses. The risks it named were hallucinations, bias, misconfiguration, cyberattacks and functional brittleness.

Deployment

Systems that pass tests and fail in use

In a September VentureBeat survey, 52% of teams that tested AI features before release saw one pass tests and then fail customers. Among agent deployers in that self-selected sample of 103, 80% of those that skipped human review reported a customer-facing failure, against 36% of those that required it; the survey does not establish cause. In August, a malicious MCP server campaign hunted for SSH keys and cloud credentials.

Who is accountable

Responsibility in the third quarter moved to whoever supplies the forecast or the engineering data. Developers that did not answer were held, PJM's cost allocation now turns on which forecast vintage is used, and in New York each utility must name the AI it runs. Utilities connecting AI agents to operational data bring those tooling attacks within the scope of NERC CIP and state cybersecurity rules.

09Regulation

Access conditions adopted or proposed in the US, Great Britain and the EU

States, governors and an RTO board made most of the quarter's decisions, with FERC ratifying and NERC writing standards. The common instrument was a condition on access: collateral, a fee, disclosure, interruptible service or a requirement to bring capacity. New York's permit hold was the exception. New York's utility AI order was the quarter's AI-specific rule for utilities, while the EU's high-risk AI duties for infrastructure moved to December 2027.

Access conditions and AI rules by jurisdiction

Dates are in 2026 unless noted. Later dates were scheduled as of Sept. 30.

Access conditions and AI rules by jurisdiction
Instrument DateWhat it requiresStatus or next date
PJM backstop and interim service Date Board July 27; FERC Sept. 29 What it requires Bring capacity or accept curtailment; 15-year backstop Status or next date Effective Feb. 28, 2027, subject to refund
FERC large-load show cause, PJM Date June 18; abeyance Aug. 14 What it requires Justify study, cost and co-location rules for 50 MW or more Status or next date PJM responses due Nov. 16
NERC computational-load standards Date FERC order, July What it requires Reliability standards for computational loads Status or next date Due by year-end 2026
Texas data-center audit directive Date Aug. 3 What it requires Disclosure and audit before any project advances Status or next date ERCOT audit filing targeted for Dec. 10
New York Executive Order 62 Date July 14 What it requires State permit hold for data centers of 50 MW or more Status or next date Until a final GEIS; release says up to a year
New York PSC utility AI order Date Sept. 17 What it requires Inventory all AI uses and file AI policies Status or next date Within 60 days
Virginia Executive Order 22 Date Sept. 18 What it requires No agency NDAs; curtailment procedures; rate structures Status or next date Legislation sought in 2027
New Jersey A796 Date July What it requires Large-load class; capacity via household efficiency Status or next date Signed
Ofgem Data Centre Commitment Fee Date July 29 What it requires £237,500 to £712,500 per MW, refunded at energization Status or next date Consultation closed Sept. 16
EU data-center rating scheme Date Sept. 21 What it requires Rate energy, water, heat reuse and flexibility above 500 kW Status or next date Two-month scrutiny; first labels in 2027
EU AI Act omnibus Date In force July 27 What it requires Defers Annex III high-risk obligations Status or next date Apply from Dec. 2, 2027

PJM

Bring capacity, or be curtailed first

The backstop buys up to 6,831 MW for terms of up to 15 years from resources that have never cleared PJM's market and will be in service by June 1, 2032. From 2029/30, large loads above the 2028/29 forecast are left out of capacity-market demand until their capacity is offered. In January, all 13 PJM governors and the White House's National Energy Dominance Council called on states to assign new capacity costs to data-center loads that bring no capacity and do not accept curtailment.

Texas

A hold pending audit, not a moratorium

The directive bars any data center in ERCOT's process from advancing until the audit is complete, requires disclosure of public support, power use, on-site generation, water, cooling and ownership, and does not use the word moratorium. ERCOT postponed Batch Zero, and BloombergNEF estimated the pause could delay 20% of the US data-center pipeline.

New York

Permit standards and a utility AI inventory

Under EO 62, the Department of Environmental Conservation holds discretionary permits for data centers of 50 MW or more until the Department of Public Service issues a final generic environmental impact statement, with exemptions including manufacturing and research such as Empire AI. The PSC will assess utilities' AI inventories and policies against AI governance frameworks.

Great Britain and EU

Fees and ratings aimed at speculative projects

Ofgem's proposed fee equals about 2.5% to 7.5% of average project cost and is forfeited if a project leaves early; contracted demand offers rose from 41 GW to 125 GW between November 2024 and June 2025. The Commission opened a consultation on minimum performance standards for data centers, running to Dec. 14, ahead of a proposal planned for the second quarter of 2027.

Liability

Collateral did the underwriting

Financial assurance carried the risk of speculative load in the quarter: AEP's Batch Zero collateral, ERCOT's security requirements, PJM's proposed collateral for load-serving entities and Ofgem's forfeitable fee. In July, Insurance Journal reported more carriers filing to use ISO's three generative-AI exclusion endorsements for general liability and products coverage.

What it changes

For utilities and developers, the practical question has moved from whether a large-load tariff exists to what data, money and controllability a project must show to keep its place in the queue.

10Voices

Where regulators, operators, buyers and critics agree and differ

Positions converge on the principle that new large loads should bring or pay for new supply. The PJM governors' January principles, Commissioner Lindsay See, NRDC, the market monitor and Virginia's order say so directly, and the Data Center Coalition accepts state-set allocation to large loads. Most also agree that request totals overstate real load. They differ on the size of PJM's gap, which depends on the forecast vintage; on who carries backstop costs and when, where buyers, wires utilities and cooperatives each describe their own zone; and on whether markets or vertically integrated utilities screen load better.

Regulators

Lindsay S. See

Commissioner, FERC

“Existing customers should not be left paying costs attributable to new demand.”

Her view matches the 13 PJM governors' January principles on assigning new capacity costs to data-center load.

Regulator · Sept. 29 concurrence

Laura V. Swett

Chairman, FERC

PJM's backstop was a deeply flawed, last-minute proposal; the commission accepted the parts needed for urgent procurement and required reform of the rest, with the region's reliability at stake.

Explains why the commission accepted the backstop subject to refund and a hearing.

Regulator · Sept. 29 concurrence

Rory Christian

Chair, New York Public Service Commission

The rapid evolution of AI is a double-edged sword for utilities.

His commission ordered the inventory after finding the extent of utility AI use unclear.

Regulator · as reported by Utility Dive

Eleanor Warburton

Director for Energy System Design and Development, Ofgem

“Where speculative projects take up space in the queue, they can delay other schemes.”

Ofgem's answer is a per-megawatt fee refunded only at energization.

Regulator · Ofgem release

Grid operators and the market monitor

David Mills

CEO, PJM Interconnection

“demand for electricity continues to grow faster than electricity supply”

PJM's board cited the gap to justify the backstop and interim service.

Grid operator · auction results release

Chad Seely

Senior vice president and general counsel, ERCOT

ERCOT will not finish the Batch Zero study by its April 9, 2027, completion date and has not asked to move the deadline, because it does not yet know how far the audit will delay the study.

ERCOT targets a Dec. 10 filing of the audit; the study delay holds the 17 near-ready loads with the rest of the queue.

Grid operator · as reported by Utility Dive

Joseph Bowring

Monitoring Analytics, PJM's independent market monitor

Data centers should contract for their own generation, with long-term auctions for those that cannot, and PJM's backstop target is outdated after about 4,017 MW of cancellations.

His figures set the low end of the dispute over the size of PJM's gap.

Market monitor · FERC comments and Utility Dive interview

Utilities, generators and oil and gas

Trevor Mihalik

CFO, American Electric Power

ERCOT's review, generation availability and transmission timelines may affect the timing of some interconnections; in a worst case, AEP's 45 GW in Batch Zero could move to the next batch.

AEP counts 45 GW of ERCOT load in its pipeline.

Utility · Q2 earnings call

Brad Viator

Power for Tomorrow

Vertically integrated utilities screen out unreal projects, and their shorter queues reflect generation ownership.

Argues the utility model handles speculative load better than restructured markets.

Utility advocacy group · as reported by Utility Dive

Drew Maloney

Edison Electric Institute

PJM's status quo benefits generation owners.

Places investor-owned utilities against the generators whose capacity revenue rose.

Utility trade group · as reported by Utility Dive

Jeff Gustavson

President, Chevron New Energies

Concern about consumer power prices moved hyperscalers toward reliable, affordable supply including gas, and Texas officials told data-center developers to bring their own power.

Explains why Chevron is supplying Microsoft behind the meter.

Oil and gas · as reported by Fortune

Data-center buyers

Dan Diorio

Data Center Coalition

A well-run Texas review could distinguish responsible data-center developers, provided it moves quickly.

The coalition also backed state-set cost allocation at FERC.

Buyer trade group · as reported by The Texas Tribune

Amazon

Hyperscaler, in FERC comments

Allocating backstop costs from a single load-forecast snapshot is inconsistent with cost causation; costs should be reallocated periodically and existing contracts grandfathered.

Buyers are contesting the forecast vintage that sets their bill.

Buyer · FERC filing

Thomas Kurian

CEO, Google Cloud

“we could obviously serve a lot more demand with capacity”

Capacity-constrained demand is what drives the power procurement in this briefing.

Buyer · Alphabet Q3 earnings call

Equipment vendors

Scott Strazik

CEO, GE Vernova

“not putting things in our order book without a firm pathway to the schedule”

A supplier with sold-out slots is guarding against reservations that do not convert if forecasts move.

Vendor · Q2 earnings call

Consumer advocates

Joint Consumer Advocates

Consumer advocates, in FERC comments

Backstop bidders could price to the cap, and the load forecast and the 15-year term need scrutiny.

Their concern is paying for long contracts sized from a forecast that may fall.

Consumer advocate · FERC filing

Claire Lang-Ree

Natural Resources Defense Council

Large loads that bring no supply should be removed from the auction and connected on connect-and-manage terms.

PJM's board adopted a version of that approach, renamed Interim Resource Adequacy Service.

Advocacy group · as reported by Utility Dive

Independent analysts

Karl Rábago

Former PUCT commissioner and consultant

The return-on-equity model rewards utilities for building infrastructure more than for scrutinizing large loads, so their load forecasts deserve skepticism.

Ties forecast inflation to the incentive in cost-of-service regulation.

Independent analyst · as reported by Utility Dive

Advait Arun

Center for Public Enterprise

The most speculative data-center predictions have collapsed, but baseline grid investment is still needed and ratepayers may end up paying for it.

Separates the forecast debate from the need for grid investment.

Independent researcher · as reported by Utility Dive

11Decisions

Three decisions for energy leaders

Utility CFO and regulatory affairs

How to report data-center load in rate cases and to investors

Commissions and market monitors are testing load figures by contract stage, and PJM's cost allocation turns on forecast vintage. A plan built on letters of agreement carries different risk from one built on service agreements backed by collateral.

Which part of our capital plan depends on load that is not yet under a service agreement, and what collateral or take-or-pay terms back it?

Grid operator or utility head of planning

Whether firm service for new large loads should depend on bringing supply

PJM's board made firm service for new large loads conditional on capacity, Texas made advancement conditional on an audit, and Ofgem proposes a forfeitable fee. Each depends on dynamic models, registry data and a tested way to curtail a facility.

If a large data center had to be curtailed ahead of emergency load management, do we have the models, telemetry and contracts to do it?

Chief information officer

How to govern AI in grid and customer operations

New York gave its utilities 60 days to inventory every AI use and file policies, and the EU's Annex III high-risk obligations, which cover infrastructure AI, apply from Dec. 2, 2027. The PJM interconnection review kept the engineering decision with a person.

Could we list every AI system we run, with its data, decision owner and human sign-off point, within 60 days?

12Actions

Four actions before the next filing deadlines

  1. 1

    Restate large-load forecasts as a stage ladder

    Report each large load as a request, study-eligible project, letter of agreement, service agreement or energized load, with dates and collateral. The result is a forecast a commission, RTO or market monitor can reconcile with its own figures.

    Load forecasting lead

  2. 2

    Make model data a condition of queue entry

    Require dynamic load models, site-control evidence and per-project disclosure at application, as ERCOT and the Texas directive now do. The result is fewer projects dropped from a study batch, as 47 were in ERCOT.

    Interconnection engineering

  3. 3

    Test a curtailment path for large loads

    Scope the telemetry, control and compensation needed to curtail a large load ahead of emergency procedures, in line with PJM's interim service and Virginia's planned curtailment procedures. The result is a curtailment exercised before the obligation applies on June 1, 2027.

    Operations technology

  4. 4

    Build the AI inventory now

    List each AI system in grid, field and customer operations with its data sources, decision owner, human review point and test record. The result is a filing ready for a New York-style order and a head start on EU obligations from December 2027.

    Chief information officer

13References

References

Covers developments from July 1 to Sept. 30, 2026. Some sources published in October report on that quarter.

Regulators, grid operators and government

Company results and filings

Trade and business press

AI capability and deployment research

Capital data

Thoughtful engineering for what’s next.

Have a question about what this means for your team? Let’s talk it through.

Start a conversation

Have a project in mind, or just exploring an idea? Let’s talk.
Fill out the form or give us a call.

413-570-3299

What can we help you with?