Regulators moved the risk of AI data-center load onto large customers as contracts grew

In the second quarter, utilities, grid operators and state commissions worked to separate data-center load that will arrive from load that has only been requested, while gas-turbine makers raised prices on the equipment that new supply depends on, with lead times of about three years. Inside the industry, AI reached a regulated workflow at PJM, where its effect has yet to be measured.

Editorial snapshot: 31 July 2026

The central finding

Signed large-load contracts kept rising while several near-term forecasts fell. Four state commissions responded by writing more of that gap's cost and risk into data-center tariffs, Texas moved to screened batch studies, and FERC ordered every regional grid operator to justify or reform its large-load rules.

01Key findings

What changed in energy and AI in the second quarter of 2026

Capability · In use

AI entered PJM's interconnection review

PJM Interconnection used HyperQ, an AI tool built by Google's Tapestry, to identify and help assess sections of application documents for further review across 811 generation projects totaling 220 gigawatts (GW). PJM will evaluate the tool's impact over Cycle 1, a review designed to last one to two years.

Capital

Gas turbines became the constraint on new supply

GE Vernova's gas-turbine backlog and slot reservations rose from 83 GW to 100 GW in the first quarter, with lead times of about three years and higher prices per kilowatt. American Electric Power (AEP) raised its five-year capital plan to $78 billion from $72 billion.

Load

Contracts grew while near-term forecasts eased

AEP reported 63 GW contracted by 2030, Southern Co. 11 GW and Dominion Energy about 10.4 GW under service agreements. Several areas assessed by the North American Electric Reliability Corp. (NERC) cut forecasts as large loads arrived more slowly than expected, and Texas requests reached 440 to 475 GW.

Accountability

States moved large-load risk onto data centers as FERC ordered rule reviews

On June 18 the Federal Energy Regulatory Commission (FERC) ordered all six regional grid operators under its jurisdiction to justify or reform their large-load rules. Wisconsin, Pennsylvania, Oregon and Minnesota approved tariffs or frameworks with terms of up to 30 years, minimum charges of 80% to 100%, collateral and exit fees.

Operating question

How much of your large-load exposure is energized, contracted, merely requested or only forecast, and who carries the cost if the difference never arrives?

02Capability

Where AI entered energy work this quarter

The structural change in energy was AI entering a regulated process step, the review of interconnection applications, where it flags document sections for further review. Elsewhere AI arrived as vendor platforms for oil and gas producers and as back-office automation at an equipment maker. Analysis by the International Energy Agency (IEA) explains why lower energy use per AI task does not settle how much power AI will need.

Grid operators · In use

AI-assisted review in PJM's interconnection queue

PJM used HyperQ, built by Google's Tapestry, to identify and help assess sections of application documents for further review in Cycle 1 of its reformed interconnection process, whose application window closed April 27. PJM expects the tool to shorten study times and will evaluate its impact over Cycle 1, a one- to two-year review.

811Generation projects in Cycle 1

220 GWCapacity applied for

Oil and gas · Vendor-announced

Agentic AI platforms sold into upstream oil and gas

SLB expanded its AI Factory for Energy with NVIDIA, a reference environment for domain-specific generative and agentic AI. ONGC will deploy SLB's Lumi platform across all its assets, Azule Energy signed a three-year platform deal, and SLB's DrillOps advisory runs on three land rigs in Qatar. The announcements describe the scope of adoption, without quantified results.

Equipment suppliers · Company expectation

AI in an equipment maker's back office

GE Vernova is applying AI to match demand with production planning, rationalize parts and match invoices, and expects savings in the tens of millions of dollars and tens of thousands of hours a year. A companywide data lake is retiring 15 legacy platforms, worth about $15 million a year. These are company projections.

Load · IEA analysis

Energy per AI task is falling, but task intensity varies widely

Google said it processed more than 3.2 quadrillion tokens a month in May. The IEA found that energy per AI task has recently fallen by at least an order of magnitude a year, but video generation and agentic tasks can use hundreds or thousands of times more energy per query, so efficiency gains alone do not settle the load question.

Model supply · June 12

A government directive withdrew two frontier models

After a U.S. Commerce Department export-control directive, Anthropic disabled access to Claude Fable 5, generally available since June 9, and Claude Mythos 5 for all customers on June 12. Utilities and grid operators running vendor models inside regulated workflows now face model availability as a supply risk that government action can change.

Cost and consequence

Where AI reached production in energy, it assisted a review step inside a regulated process. The practical costs sit around the model: developers' site-control and readiness documents need to be machine-readable, operators need an audit trail from each AI-assisted finding to the reviewer's decision, and any workflow built on one external model needs a fallback.

03Capital

Capital went to turbines, transmission and regulated rate base

Capital followed the physical bottleneck. Turbine and grid-equipment makers captured price and margin; utility capital plans, which earn a regulated return, grew at AEP and held steady at Dominion; and hyperscalers' spending supplied the demand behind both. The sharpest signal is the gap between gas-turbine reservations and firm orders at the largest supplier.

19 GW

New gas-turbine slot reservations at GE Vernova in the first quarter

A reservation holds a factory slot before a firm order is placed.

2 GW

New gas-turbine orders at GE Vernova in the same quarter

Another 6 GW of earlier reservations converted to orders.

Capital plans and order books reported in the quarter

First-quarter results and capital plans reported April 22 to May 12, 2026, in each company's reporting currency.

Capital plans and order books reported in the quarter
Company MeasureReported valueChange
AEP Measure Capital plan, 2026–2030 Reported value $78B Change Up from $72B
Dominion Energy Measure Five-year capital plan Reported value About $65B Change Unchanged
GE Vernova Measure Orders; total backlog Reported value $18.3B; $163B Change Orders up 71% organically
GE Vernova gas turbines Measure Backlog plus slot reservations Reported value 100 GW Change Up from 83 GW
Siemens Energy Measure Orders; backlog Reported value €17.7B; €154B Change Record orders; book-to-bill 1.72
SLB Measure Digital annual recurring revenue Reported value $1.02B Change Up 15%

Siemens Energy's figures are for its fiscal second quarter, January to March 2026.

Gas turbines

GE Vernova raised turbine prices and is adding capacity in steps

GE Vernova's chief executive said first-half 2026 gas orders were priced 10 to 20 points higher per kilowatt than orders in late 2025, with lead times of about three years. Factory capacity rises to about 20 GW a year by the third quarter of 2026 and 24 GW in 2028. About 20% of the 100 GW of gas backlog and reservations is explicitly for data centers.

Grid equipment

Electrification and data-center orders rose fastest

GE Vernova's electrification orders rose 86% to $7.1 billion, and its data-center equipment orders of $2.4 billion exceeded its total for all of 2025. Siemens Energy raised its revenue-growth outlook to 14% to 16%, from 11% to 13%, and its free-cash-flow outlook to about €8 billion.

Utilities

Rate base grows with the contract book

AEP raised its five-year plan to $78 billion, expects rate base to grow about 11% a year to 2030 and has line of sight to more than $10 billion of further projects kept outside the plan pending regulatory clarity. Under cost-of-service regulation, that capital earns a return, so the question of who funds it moved to tariff dockets.

Oilfield services

SLB's fastest-growing line served data centers

SLB's Data Center Solutions revenue rose 45% to $141 million in the first quarter, as a modular design partner for NVIDIA's DSX AI factories, while its Middle East revenue fell. SLB also said it plans to buy S&P Global Energy's geoscience and petroleum-engineering software business and add agentic AI, with closing expected in the second half of 2026 or early 2027.

Buyers

Hyperscaler capital spending behind the order books

Alphabet, Amazon, Meta and Microsoft together reported about $166 billion of capital expenditures from April to June (Meta's figure includes finance-lease payments), and hyperscaler-related bonds reached $225 billion by midyear. That spending underlies the data-center share of the turbine reservations and utility contract books above.

What it signals

The supplier of the scarcest equipment is more cautious than its customers: GE Vernova is raising prices, adding factory capacity in steps and has closed none of the 30 to 35 long-term framework agreements under discussion, while buyers reserve slots and build on site. For utilities, equipment lead times of about three years now set the earliest date contracted load can be served, which is why AEP's chief financial officer tied the timing of its Texas load to the generation built to serve it.

04Supply and products

How power for AI load is being supplied

The quarter's most prominent supply deal had an oil major developing a dedicated gas plant for a hyperscaler, still awaiting a final investment decision. Grid operators changed how large loads are studied and matched with generation. AI tools arrived in grid and oilfield workflows as named deployments with a status but no results.

Large-load buyers · Self-supply

Self-supply moved behind the fence

Chevron's agreement with Microsoft and the on-site gas plants built or planned for Meta, Poolside AI and Pacifico Energy's Fort Stockton site put generation behind the fence. Supply arranged this way reduces reliance on grid power but depends on the same gas turbines, with lead times of about three years.

Engineering

On-site generation moves grid engineering to developers

Co-located and behind-the-meter supply shifts islanding, ride-through settings, curtailment telemetry and the metering needed for FERC's co-located and nearby-load categories from the utility to the developer and its vendors. The Electric Reliability Council of Texas (ERCOT) generally treats islanded sites as outside its interconnection process.

Grid operators

Operators began matchmaking for new supply and batching large loads

PJM launched a facilitated bilateral matchmaking process for buyers and sellers of new supply through a request for proposals on June 9. ERCOT's Batch Zero, approved by Texas regulators on June 18, studies all qualified loads of 75 megawatts (MW) or more together, with pathways for on-site generation and curtailable service.

Selected supply arrangements and launches in the quarter

Dates are announcement, approval or reporting dates within the quarter; status is as reported at the time.

Selected supply arrangements and launches in the quarter
Arrangement DateScaleStatus at the time
Project Kilby (Chevron, Engine No. 1, Microsoft) Date June 22 Scale About 2.67 GW of gas; 20-year agreement Status at the time No final investment decision; power targeted 2028 Equipment from GE Vernova and Solar Turbines; Permian gas
Meta, New Albany, Ohio Date Reported June 10 Scale Two 286.5 MW on-site gas plants Status at the time Due in 2026 and early 2027
Poolside AI Date Reported June 10 Scale 576 MW and 246 MW of on-site gas Status at the time — No comparable figure
Pacifico Energy, Fort Stockton, Texas Date Reported June 10 Scale 1,300 MW of gas plus 500 MW of batteries Status at the time Construction later in 2026; power in 2028 Site could host more than 6 GW
PJM bilateral matching Date June 9 Scale Buyers matched with sellers of new supply Status at the time Launched through a request for proposals
ERCOT Batch Zero Date June 2 board vote; June 18 approval Scale Loads of 75 MW or more studied together Status at the time Approved; classifications due in August
PJM Cycle 1 with HyperQ Date Window closed April 27 Scale 811 projects, 220 GW Status at the time AI-assisted review in use
SLB Lumi at ONGC Date April 24 Scale All ONGC assets Status at the time Announced

— No comparable figure.

What it changes

Power for AI load is increasingly contracted outside utility tariffs, while utilities and grid operators keep the reliability obligation. The technical interface between a self-supplied site and the grid, including curtailment signals, ride-through settings and metering, now needs the same specification and testing as the supply contract.

05Load and adoption

Measured, contracted, requested and forecast data-center load

Four numbers describe data-center load, and the quarter makes sense only when they are kept apart: electricity actually used, load under signed agreements, interconnection requests and planning forecasts. Data-center use showed up in first-quarter sales and contract books grew, while requests ran far above contracts. AI adoption inside utilities was broad but shallow, and the economic contest was over who pays for the grid that large loads require.

Data-center load by measure

Measured use is electricity actually sold or consumed; contracted is load under signed agreements; requested covers interconnection requests and utility pipelines; forecast is a planning projection. Utility figures are from first-quarter results reported April 30 to May 5, 2026.

Data-center load by measure
Utility or agency Measured useContractedRequested or pipelineForecast
Southern Co. Measured use Data-center use up 42% in the first quarter Contracted 11 GW across 28 projects Up from 10 GW at the end of 2025; 6 GW more being finalized Requested or pipeline 75 GW prospective pipeline Forecast — No comparable figure
AEP Measured use Commercial sales up 15.8% (integrated), 33.3% (wires-only) Contracted 63 GW by 2030 Up from 56 GW; includes 41 GW under Texas letters of agreement Requested or pipeline About 60 GW in its ERCOT queue Forecast — No comparable figure
Dominion Energy (Virginia) Measured use Commercial sales up 8.4%, mostly data centers Contracted About 10.4 GW under service agreements Requested or pipeline About 51 GW in contracting stages Forecast — No comparable figure
ERCOT (Texas) Measured use May peak of 77,822 MW, below May 2025's 78,399 MW Contracted — No comparable figure Requested or pipeline About 410 GW by early April; 440–475 GW by June Forecast 2032 peak of 367,790 MW, set aside for planning
NERC (North America) Measured use — No comparable figure Contracted — No comparable figure Requested or pipeline — No comparable figure Forecast Summer peak up 11 GW on 2025; several areas revised down
U.S. Energy Information Administration (EIA) Measured use — No comparable figure Contracted — No comparable figure Requested or pipeline — No comparable figure Forecast 4,271 billion kWh in 2026, up 1.8% Commercial sales up 3.6%, revised from 2.2% in May; EIA cites data centers and large manufacturing in Texas and Virginia
IEA (global) Measured use 485 TWh used by data centers in 2025, up 17% Contracted — No comparable figure Requested or pipeline — No comparable figure Forecast About 950 TWh by 2030

Pipelines are not comparable across utilities: Dominion's includes early contracting stages, Southern's is prospective, and AEP's contracted total includes Texas letters of agreement that are not take-or-pay contracts. ERCOT request totals are successive snapshots; data centers account for about 90% of requested megawatts and about 70% of projects.

Vertically integrated utilities

Data-center load is visible in sales

Southern's chief financial officer called its 2.3% first-quarter retail-sales growth the highest for a first quarter in recent history, and weather-adjusted commercial sales rose 4.5%. Dominion's Virginia sales rose 4%. For these utilities, part of the contract book is already energized and billing.

Wires-only utilities

Fastest growth on the transmission and distribution side

AEP's wires-only utilities showed the fastest measured commercial growth in the comparison above. Wires-only utilities carry the kind of transmission build that PJM-state consumer advocates are contesting, which turns customer-level cost tracing into a data and metering task.

Grid operators

Forecasts now need to separate screened load

With requests far above contracts, ERCOT was directed to base its adjusted long-term forecast on screened Batch Zero load, and PJM began matchmaking buyers with sellers of new supply. Both require forecasting systems that track each megawatt from request through screening, study and contract.

Utilities' own AI use · April 2026 survey

Broad adoption, mostly pilots

Deloitte surveyed executives at 60 investor-owned utilities in more than 40 states. Use is broad, but few report mature use of AI and geospatial tools for grid resilience, where technology spending rose 38% from 2023 to 2025, to more than $8 billion. Deloitte sells AI and geospatial services.

100%Piloting or deploying traditional AI

68%Generative AI

38%Agentic AI

10%High maturity in resilience

Oil and gas

An oil shock alongside a new customer class

Very limited shipping through the Strait of Hormuz had cut Middle East crude production by more than 11 million barrels a day in May, according to EIA, and Brent crude averaged $117 a barrel in April. SLB demobilized in several countries and Qatar declared force majeure, while oil companies such as Chevron moved into supplying power to data centers.

Wholesale prices

PJM wholesale prices rise while ERCOT's fall

EIA's June outlook forecasts PJM Western Hub prices of $73.37 per megawatt-hour in 2026, up from $60.09 in 2025, while ERCOT North falls from $37.33 to $35.74. Coal generation in PJM rises against a national decline.

Consumer advocates

Advocates trace PJM costs to data centers

Maryland's People's Counsel cited the PJM market monitor's estimate of $23 billion in added capacity costs over the last three auctions and described $22 billion of baseline transmission spending across three planning rounds as overwhelmingly for data-center growth, $2 billion of it borne by Maryland customers. In auctions held before the quarter, PJM capacity prices rose from $28.92 per megawatt-day to $269.92 for 2025-26 and $329.17 for 2026-27.

Utilities

Utilities project offsets for existing customers

AEP projects up to $16 billion of offsets for existing customers from large-load contracts' share of fixed costs. Dominion expects long-term bill growth to track inflation and says large-load provisions approved in its 2025 biennial review are meant to keep smaller customers from subsidizing its largest customer classes.

Economics

Under cost-of-service regulation, the contract book converts into rate base and earnings, while the price risk stays with existing customers unless tariffs move it. That is why the quarter's economic contest was over minimum bills and collateral. No AI tool inside an energy company reported a measured effect on margin, price or capacity in the quarter.

06Outcomes

Results from observed load and early AI deployments

The quarter's clearest measured results came from operators observing how data centers behave and how much new supply arrived. The AI deployments in energy operations reported scope and expectations; none of those described in this briefing came with a measured result.

ERCOT · Forecast revision

ERCOT cut its summer forecast after modeling data centers

ERCOT lowered its summer 2026 demand forecast after modeling how large computational loads actually behave at peak and counting more curtailable data centers, according to NERC's May assessment. Its May peak also stayed below the May 2025 record.

Scope: A forecast change, not measured curtailment.

1.9 GWLower total internal demand (2.3%)

3.7 GWLower net internal demand (4.6%)

NERC · Summer assessment

New supply arrived at scale

NERC's count of new resources includes 19.0 GW of other resource types and availability changes. It found all areas adequate under normal peak conditions, with elevated risk of shortfalls in its New England, SaskPower and WECC Northwest assessment areas and operational concerns in Far West Texas.

More than 58.5 GWNew resources since summer 2025

16.4 GWSolar counted at peak, of 30.5 GW installed

AI in operations · Not yet measured

AI results were reported as scope or expectations

PJM will evaluate HyperQ's impact over Cycle 1. GE Vernova expects internal AI to save tens of millions of dollars a year. SLB's chief executive said customers are seeing performance and efficiency effects from its AI tools, without published figures.

What held up

ERCOT's forecast changed when it modeled data-center behavior it could observe. AI in operations has not yet had a comparable test: the first deployment to publish a measured result against its prior process will set the benchmark for the others.

07Corrections

Four common claims about AI and the grid, corrected

Each correction turns on a distinction that changes how a figure should be used in planning or in a rate case.

Texas load · Requests, not demand

Texas has 440 to 475 GW of large-load requests, and Texas regulators set aside ERCOT's own 368 GW long-term forecast for planning.

Claim under review: Texas faces more than 400 GW of new data-center demand.

Texas officials reported roughly 410 GW of large-load applications to a state Senate committee by early April, and ERCOT counted 440 to 475 GW by June, about 90% of it from data centers by megawatts. Its April preliminary forecast put the 2032 peak at 367,790 MW, against a record of 85,508 MW. ERCOT reported that few stakeholders considered that figure credible for planning, and at its June 18 open meeting the Public Utility Commission of Texas directed ERCOT to base the adjusted long-term forecast on the screened Batch Zero load, expected in mid-August.

Federal rule · Inaccurate

FERC ordered all six regional grid operators to justify or reform their large-load rules and left the national rulemaking open.

Claim under review: FERC issued a national large-load interconnection rule in June.

On June 18, FERC answered the Department of Energy's October 2025 directive with Section 206 show-cause orders to the six regional transmission organizations and independent system operators (RTOs and ISOs) and their transmission owners. The orders are meant to protect existing agreements, and rulemaking Docket No. RM26-4-000 remains open, so a national rule is still possible. Because the orders act on RTO transmission tariffs, they leave aside, for now, the state–federal question of who governs retail-load interconnection.

Nuclear supply · Overstated

Hyperscaler nuclear deals total up to about 13 GW: 6.9 GW of power purchase agreements and 6.1 GW of partnerships, with most new reactors due between 2032 and 2039.

Claim under review: Hyperscalers are powering AI with new nuclear plants.

The Carnegie Endowment found the purchase agreements mostly with existing plants and partly contingent on Nuclear Regulatory Commission approvals, and the partnerships often limited to modest investment, site commitments or rights to future units. Even if every planned reactor is built, the deals would supply about 102 TWh a year, under 20% of projected demand through 2035.

Household bills · Needs a regional distinction

EIA forecasts a 5.4% rise in U.S. residential prices for 2026 without attributing it directly to data centers; the attribution case is regional.

Claim under review: Data centers are driving up household electricity bills nationwide.

EIA's June outlook puts the 2026 residential average at 18.23 cents per kilowatt-hour. Its May edition said East Coast residential prices could rise up to 7% a year over two years and did not attribute the increases directly to data centers. The specific attribution claims come from the PJM region, where consumer advocates tie capacity and transmission costs to data-center growth and want those costs assigned to the customers who cause them.

08Accountability

Failure mechanisms: load loss, queue overload and stalled AI projects

The quarter's documented failures were in how the grid absorbs data centers. AI projects inside energy companies show a separate failure pattern, rooted in data access.

Reliability · Reported events

Data centers dropping off the grid during voltage dips

NERC's summer assessment reported voltage-sensitive load reductions of about 1,500 MW in each of the Eastern and ERCOT interconnections, the Eastern one mainly data centers switching to backup power. NERC's State of Reliability report counted 2025 data-center load reductions including two above 1,000 MW, and WECC's Northwest area has seen frequency problems from sudden large-load disconnection. ERCOT requires ride-through capability and dynamic models for large loads.

Interconnection · Process failure

A queue built for a fraction of the requests

ERCOT received 225 new large-load interconnection requests in 2025, according to a December report, while its process was built for a queue of 40 to 50 projects. ERCOT's Jeff Billo told its board on June 2 that the process was not designed for that volume, and Texas replaced individual load studies with Batch Zero.

Planning · Forecast overshoot

Forecasts ran ahead of arrivals

NERC reported that several areas lowered their load forecasts from mid-2025 levels because some large loads are coming online more slowly than expected, even as utilities' contract books grew. In October 2025, before the quarter, Maryland's People's Counsel had called utility submissions that roughly doubled PJM's 2030 data-center forecast, to about 60 GW from 33 GW, overstated.

AI projects · Published March 31, before the quarter

Energy-sector AI projects were terminated more often

In a 451 Research survey of IT and business staff at utilities and oil and gas companies, 9% of the past year's AI projects were decommissioned after deployment. System integration, data quality and data access were the most cited technical problems; 54% of organizations reporting data-access problems said they hurt timelines, scope or performance, and 15% said they halted an initiative. In April, more than half of utilities without centralized geospatial systems cited disconnected data as their main barrier.

34%Energy AI projects terminated

26%All-sector average

AI agents · Risk

Agents connected to operational systems

Cloud Security Alliance research notes reported a design flaw in the Model Context Protocol software kit exposing about 200,000 instances, and an injection attack that succeeded against tested AI coding agents 85% of the time. The documented cases involve software tools, not grid systems, but the mechanism applies to agents connected to outage, work-management or operational technology systems covered by NERC's Critical Infrastructure Protection standards.

Who is accountable

Each response puts the failure on the party that controls it. Ride-through and dynamic-model requirements make a data center's grid behavior its owner's responsibility, batch studies put queue discipline on applicants, and PJM uses its AI tool to flag document sections for further review within a process PJM still runs. Utilities wiring AI into operations should expect the same test: who controls the step, and who answers for it.

09Regulation

Large-load rules in the US and AI rules in the EU

U.S. regulators acted on cost allocation and interconnection rather than on AI itself. FERC chose targeted orders over a national rule, four state commissions wrote stranded-cost protection into tariffs, and Texas moved to batch studies. In the EU, the AI Act's provisions for AI in electricity and gas supply remained legally scheduled for Aug. 2, 2026, while a delay adopted by Parliament and the Council in June awaited publication.

Federal · Responses due Aug. 17, 2026

FERC's show-cause orders to six grid operators

FERC's June 18 orders give PJM, MISO, SPP, CAISO, ISO-NE and NYISO, with their transmission owners, 60 days to justify or change rules in five areas: transmission-service studies, including alternative transmission technologies; preventing cost shifts; co-location and behind-the-meter generation; new services for flexible large loads; and studying generation that serves nearby or co-located loads. Utilities outside RTOs were encouraged to file under Section 205.

Texas · Approved June 18

Batch study, curtailment and proposed deposits in Texas

Batch Zero classifications follow in August, Batch 1 applications in summer 2027 and a transmission plan in fall 2027, with firm power not expected before 2028. Under Texas law, loads of 75 MW or more interconnecting from 2026 must accept curtailment during firm load shed. Commission proposals reported in early April included deposits of $50,000 per MW and forfeiture of about 80% of security on downsizing or withdrawal.

EU AI Act · Statutory date Aug. 2, 2026

AI that acts as a safety component in energy supply

Annex III treats as high-risk AI intended as a safety component in managing and operating critical digital infrastructure, road traffic or the supply of water, gas, heating or electricity. The Digital Omnibus, agreed provisionally on May 7, moves these obligations to Dec. 2, 2027. Parliament adopted it on June 16 and the Council on June 29, but it had not been published by June 30, so Aug. 2, 2026, remained the legal date. Control-room and protection AI may qualify; general analytics typically would not.

EU efficiency rules · Consultation closed April 23

Data-center energy and water reporting in the EU

Under the Energy Efficiency Directive, data centers with significant energy use report energy and water indicators to a European database under Delegated Regulation (EU) 2024/1364. The European Commission took feedback on draft rules for a common rating scheme from March 26 to April 23, 2026, and began a 24-month study on minimum performance standards early in the year.

State large-load tariff decisions, April 24 to May 15, 2026

Large-load tariff decisions by four state commissions during the quarter.

State large-load tariff decisions, April 24 to May 15, 2026
Commission Applies toTermMinimum chargeExit and other terms
Wisconsin PSC (WEPCO), April 24 Applies to Very large customers Term 15 years including ramp, up from 10 Minimum charge Higher of 100% of forecast load or actual demand Exit and other terms Unrecovered costs plus up to two years of charges Covers non-recoverable preparation costs or remaining net book value
Pennsylvania PUC, May 13 orderModel framework for future utility filings; self-build allowed. Applies to Over 50 MW individually or 100 MW in aggregate Term Guidance on ramps and minimum terms Minimum charge Deposits and collateral against stranded costs Exit and other terms Exit guidance; large loads pay interconnection costs
Oregon PUC (PGE Schedule 96), May 7 Applies to Over 20 MW Term 10 years; 30 years at 220 MW or more Minimum charge Demand charges at 90% of contracted capacity Generation and transmission demand charges Exit and other terms Surcharge of 1 cent per kWh above 100 MW Pays 100% of distribution upgrades; emissions condition under the POWER Act; effective June 10
Minnesota PUC (Xcel Energy), May 15 Applies to Large data centers Term 15-year default; 24-month notice Minimum charge Greater of actual on-peak demand or 80% of contract Exit and other terms Fee of 80% of on-peak demand charges Over the lesser of the remaining term or 120 months

For context, a national tracker counted 77 large-load tariffs or service rules from 60 utilities in 36 states as of March 31, 2026, 29 of them approved in 2025, against 14 from 2018 to 2024.

Dates set or scheduled during the quarter

Dates published by June 30, 2026. FERC's deadlines run 30 and 60 days from the June 18 orders; the Dec. 2, 2027, date applies once the adopted Digital Omnibus is published in the Official Journal.

Dates set or scheduled during the quarter
Date What happensBody
July 20, 2026 What happens Resource-adequacy reports from the six RTOs and ISOs Body FERC
Aug. 2, 2026 What happens AI Act general application; Annex III unless delay published Body EU
Aug. 17, 2026 What happens Show-cause responses due Body FERC
August 2026 What happens Batch Zero classifications; rebased long-term forecast Body ERCOT and PUCT
Sept. 16, 2026 What happens Stakeholder comments on RTO filings Body FERC
End of 2026 What happens Expected final investment decision on Project Kilby Body Chevron
Dec. 2, 2027 What happens Annex III obligations once the Digital Omnibus is published Body EU
Summer and fall 2027 What happens Batch 1 applications; Batch Zero transmission plan Body ERCOT
2028 What happens First power targeted at Kilby and Fort Stockton Body Developers

What it changes

In a rate case, these tariff terms now determine what a signed large-load contract is worth to other customers: term, minimum charge and exit fee set how much stranded-cost risk stays with them. For RTOs, Aug. 17 is the date by which each must defend its large-load rules or propose new ones.

10Voices

Where regulators, utilities, buyers and skeptics agree and differ

Most positions converge on three points: large loads should carry their own costs, interconnection requests overstate the load that will arrive, and firm supply is short now. Regulators, utilities and consumer advocates share the first principle and differ on mechanism. They divide on how much load arrives: Dominion sees no slowing in data-center demand, while several NERC areas cut forecasts and a Texas energy-business group expects many requests never to be built. Part of that gap is a difference of horizon: utilities describe multiyear contract books, NERC next summer's peak. On who should procure power for data centers, Maryland's People's Counsel wants data-center load out of PJM's markets and planning and AEP is weighing its PJM options, while FERC and the Department of Energy want RTOs to integrate large loads faster, with protection against cost shifts. On nuclear, hyperscaler announcements imply a large role this decade; Carnegie's analysts and Southern's chief executive place it later. The leading turbine supplier is adding capacity in steps and has closed no long-term framework agreements while buyers reserve slots and build on site, which suggests the supplier discounts the durability of demand more than its customers do.

Federal and state regulators

Laura V. Swett

Chairman, Federal Energy Regulatory Commission

Swett said in April that FERC was addressing large-load interconnection head-on, and in June chose orders requiring each RTO to justify or reform its rules. Her concurrences argue that this approach delivers reform faster than a national rulemaking would.

The rulemaking docket stays open, so a national rule remains possible.

Regulator · commission releases and concurrences

Chris Wright

U.S. Secretary of Energy

“America is entering a period of unprecedented electricity demand”

Wright presented FERC's June 18 orders as delivering the administration's Ratepayer Protection Pledge. Deputy Secretary James P. Danly called them a step toward better interconnection that guards existing customers against cost shifts.

Federal government · Department of Energy statement

Steve DeFrank

Chairman, Pennsylvania Public Utility Commission

DeFrank described a level of load growth not seen in generations and said the framework protects existing ratepayers from the financial risks of that new demand.

His commission's model tariff gives Pennsylvania utilities a template for large-load filings.

State regulator · commission release

Reliability bodies and grid operators

John Moura

Director of reliability assessment and system analysis, NERC

Moura said better summer conditions should not be read as lower overall reliability risk.

Grid Strategies, below, reads the same assessment as showing more headroom than NERC reported.

Reliability body · reported remarks

Jeff Billo

Vice president of interconnection and grid analysis, ERCOT

Billo said ERCOT's previous large-load process was not built for the volume of requests it now receives, and that Batch Zero is meant to separate mature projects from speculative ones.

Grid operator · reported remarks

Utilities and cooperatives

Bill Fehrman

Chairman, president and CEO, American Electric Power

On AEP's first-quarter call, Fehrman said the company is evaluating its options in PJM, including staying, shifting or alternative structures, while stressing that it has not decided to leave, and said he had little confidence that interconnection problems would be solved soon.

AEP's contracted load still rose to 63 GW in the same quarter, so the reservation concerns market structure and timing rather than demand.

Utility executive · earnings call transcript

Chris Womack

CEO, Southern Co.

Womack reported strong momentum from large-load customers but said Southern was not ready to commit to building a new nuclear unit.

The clearest incumbent check on the nuclear timeline that hyperscaler announcements imply.

Utility executive · reported earnings call

Bob Blue and Steven Ridge

CEO and CFO, Dominion Energy

Blue said uncertainty over PJM capacity prices and cost allocation had produced no detectable slowing in data-center demand in Virginia, and Ridge described Dominion's data-center customers as high quality and low risk.

This is the strongest demand view among the utilities in this briefing, set against NERC's forecast revisions.

Utility executives · earnings call transcript

Jim Matheson

CEO, National Rural Electric Cooperative Association

“NERC's findings once again show that grid reliability risks persist”

Cooperatives answer to members rather than shareholders but face the same question of who pays for large-load growth.

Cooperatives' association · own publication

Suppliers and vendors

Scott Strazik and Ken Parks

CEO and CFO, GE Vernova

Strazik said GE Vernova had closed none of the 30 to 35 long-term framework agreements under discussion and would learn more about when the market needs additional turbines as it sells its remaining 2029 and 2030 slots; Parks pointed to the company's disciplined underwriting.

The leading gas-turbine supplier's caution sets the pace for utility-built and self-supplied gas generation alike.

Vendor · company webcast transcript

Olivier Le Peuch

CEO, SLB

Le Peuch said SLB's customers are seeing performance and efficiency effects from its AI and digital tools.

Vendor · earnings release

Buyers

Andy Jassy

CEO, Amazon

On Amazon's July 30 call on second-quarter results, Jassy said capacity additions were helping drive AWS's accelerating growth and that Amazon would not have enough capacity to meet all of its 2026 demand.

AWS revenue grew 37% in the quarter. GE Vernova's three-year turbine lead times and NERC's call for more firm, dispatchable resources point the same way as Amazon's capacity shortfall.

Buyer · July 30 earnings call, as reported by Fortune

Consumer advocates

David S. Lapp

Maryland People's Counsel, for the Consumer Advocates of PJM States

“map every cost directly to its data center causer”

On May 13 he asked the PJM Board to exclude data-center load from markets and planning unless its costs can be traced to the data center that causes them, and said data centers should bring new capacity matching their hourly needs.

Consumer advocate · remarks to the PJM Board

Researchers, analysts and skeptics

John Pendleton and Mackenzie Schuessler

Carnegie Endowment for International Peace

“Signing up for the marathon does not move the sprint’s finish line.”

Their June 2 analysis found hyperscaler nuclear commitments split roughly evenly between power purchase agreements and partnerships, with most new reactor capacity arriving after 2030.

Think tank · published analysis

Arushi Sharma Frank

Center for Strategic and International Studies

Sharma Frank reported Texas officials' count of 410 GW of load applications, nearly 90% from data centers, listed phantom load growth among the problems Texas must solve, and wrote that Batch Zero projects would get no firm power before 2028.

Think tank · published analysis

Adria E. Brooks

Grid Strategies

“suggests the two regions are also resource adequate under extreme conditions”

Using Lawrence Berkeley National Laboratory queue data, her July 6 review of NERC's May assessment found every region carrying 5% to 93% more reserves than its target, including New England and the Northwest, the two regions NERC flagged for extreme conditions. Grid Strategies consults for transmission and clean-energy clients.

Consultancy · published review

Matthew Boms

Texas Advanced Energy Business Alliance

Boms said many Texas requests will never materialize and that regulators need to separate real projects from paper projects.

Trade association · reported interview

Bank for International Settlements

International financial institution

“These episodes ended with an eventual reversal in investment, inducing economy-wide recessions.”

The BIS compared the AI capital-spending cycle with past booms, from the 1840s railway mania to the late-1990s dotcom boom, and warned that competition could push firms to over-commit, the scenario that minimum bills, long terms and exit fees are designed to protect utility customers against.

International institution · annual economic report

11Decisions

Three decisions for utility, grid and technology leaders

Utility CFO and regulatory affairs

How much of the large-load book to build for

Contract books grew in the quarter, but they mix take-or-pay service agreements, Texas letters of agreement and prospective pipelines, while near-term forecasts eased. The new state tariffs give utilities tools to hold large customers to their forecasts: minimum charges, long terms, collateral and exit fees.

Which share of planned capital is backed by take-or-pay contracts with collateral, and what happens to rate base and customer bills if the rest arrives two years late?

RTO and ISO planning leads

Whether to defend or reform large-load rules by Aug. 17

FERC's orders require each RTO to justify or change its rules in five areas within 60 days. ERCOT's experience shows the cost of planning on raw requests; PJM's bilateral matchmaking, which pairs buyers with new supply, and ERCOT's Batch Zero, which studies only qualified loads, show two ways to bring large loads into the plan.

Can our large-load forecast show, for every megawatt, whether it is requested, screened, studied, contracted or energized?

CIO or chief digital officer

What AI must show before it counts in a regulated process

PJM's use of HyperQ shows the pattern regulators will see first: a tool that flags material for further review, inside a process the operator still runs, with its impact not yet measured. Utilities adding agents to outage, work-management or operational technology systems also take on model-availability and tool-security risks, and EU operators face high-risk obligations if the AI acts as a safety component.

For each AI tool in a regulated or operational workflow, can we show the decision trail, a measured result against the prior process and a fallback if the model is withdrawn?

12Actions

Four actions for the third quarter

  1. 1

    Restate the large-load book in four columns

    Report measured, contracted, requested and forecast load separately to planning, finance and regulators, with the contract type and collateral behind each contracted megawatt. The result is a forecast that holds up under the scrutiny FERC and state commissions now apply.

    Load forecasting lead

  2. 2

    Map contracts against the new tariff terms and FERC's five areas

    Compare existing large-load agreements with the terms Wisconsin, Minnesota, Oregon and Pennsylvania adopted and with the five areas in FERC's orders. The result is a gap list ready before RTO filings on Aug. 17 and stakeholder comments on Sept. 16.

    Regulatory affairs

  3. 3

    Require ride-through data from large loads

    Ask large-load customers for ride-through settings and dynamic models, as ERCOT requires, and log every voltage-sensitive load reduction. The result is a planning model that includes load-loss events on the 1,500 MW scale NERC reported.

    Transmission and reliability engineering

  4. 4

    Inventory AI in operational and regulated steps

    List each AI tool by workflow, decision owner, model vendor and fallback, flag tools that could be safety components under the EU AI Act, and set a baseline measure before expanding any of them. The result is a before-and-after comparison for every tool that grows.

    CIO

13References

References

Covers April 1 to June 30, 2026, using sources published by July 31, 2026, including first-quarter company results reported in April and May and second-quarter results reported in late July. U.K. and Irish connection policy, public power and cooperative load data, and energy-specific venture funding are outside this edition's coverage.

Regulation and reliability

Grid operators and energy data

Company results and deals

Advocates, researchers and analysts

Thoughtful engineering for what’s next.

Have a question about what this means for your team? Let’s talk it through.